From:                                                       Amoah, Alison

Sent:                                                         01 February 2022 21:32

To:                                                            Amoah, Alison

Subject:                                                   FW: GPV Ph4: Piling approvals Condition 48 App.Con 220022

Attachments:                                         Roger Bulliant Design Calculations GPV Ph4 MG.18.7221.pdf

 

 

 

Regards,


Alison

 

Alison Amoah

Principal Planner

Planning, Directorate for Economic Growth and Neighbourhood Services

 

Reading Borough Council

Civic Centre

Bridge Street

Reading RG1 2LU

 

0118 937 2286 (72286)

07855 125859

 

From the 1st April 2017 we will be charging for copies of decision notices, site history searches and s106 enquires

 

This Council implemented its Community Infrastructure Levy (CIL) on 1st April 2015.  Planning  applications may be liable to pay the levy.  For more information please visit our website at http://beta.reading.gov.uk/readingldf

 

Website | Facebook | Twitter | YouTube | Instagram | LinkedIn

 

cid:image001.jpg@01D5FB9F.180D6300  cid:image002.jpg@01D5FB9F.180D6300 

 

From: Tim Salt <Tim.Salt@berkeleygroup.co.uk>
Sent: 17 January 2022 12:52
To: Amoah, Alison <Alison.Amoah@reading.gov.uk>
Subject: RE: GPV Ph4: Piling approvals Condition 48 App.Con 220022

 

Alison,

 

As have been submitted and approved, the vibro stone column ground improvement foundation solutions to the houses of Phases 1, 3a 3b & 5 all confirm the termination of the columns in the River Terrace deposits, not the Lambeth group layers.

 

I can confirm Phase 4 is no different in the column terminations implementing the same housing designs on this phase.

The resubmitted Rambolls report 1620000492 Green Park Village Piling Risk Assessment R002 , approved on earlier phases, confirms the same risk profile to the underlying soils to Phase 4 (Section 8 – Page 24)

Within Phase 4 the founding methodology is proposed to comprise vibro-stone columns that will terminate within the River Terrace Deposits. At this stage (the time of publication) the termination depth has not been finalised, however, this is anticipated to be at a similar depth to Phase 3 at approximately 4.0 m below land raise level ~36.2 mAOD.

I can confirm with the attached Pile Design Roger Bullivant Design Calculations GPV Ph4 MG.18.7221 (not provided prior to the determination of App.Con 180968) that they have considered the same depth allowances  “the design calculations highlight that a target depth of around 3.0m will provide suitable settlement controls against the loadings detailed in section 5. Due to ground conditions and working levels anticipated, column lengths in the range of 2.5m to 3.5m will be expected” – these all are within the River Terrace Deposits following placement of approved the capping materials needed to address the flood levels.

 

The Foundation Risk assessment provided by Ramboll, confirms a Low Risk for contamination pathways as with other adjacent phases.

 

I trust this statement allows you to clear the condition.

 

Regards

 

Tim Salt

Technical Director